Project Background
Ogilvie Ridge Project Background
In early 2022, the City of Edmonton issued a competitive property listing for the sale of a 2.0-acre land parcel at 909 Ogilvie Boulevard. This listing was part of the City of Edmonton Building Housing Choices program, encouraging the development of surplus school lands.
Through this process, HomeEd was selected, and construction of an innovative new townhome development is now underway, drawing inspiration from welcoming, family-friendly homes that fit seamlessly into the existing community. Our Ogilvie Ridge townhomes will help to foster a strong sense of community and provide residents with safe, comfortable homes.
Development Timeline
Site Servicing Start
Construction Start
Estimated Completion


Development Features
Designed for Families,
Built for Community
Affordable Living
As a mixed-market housing site, 50% of the planned 70 units will be available at below-average market rent to tenants and families with a qualifying household income.
Sustainable Builds
Homes will be designed to meet the Tier 3 NECB 2020 energy standard, with design features and products built for durability and resilience.
Inclusivity Through Accessibility
14 accessible homes with one- and two-bedroom layouts, specifically designed to accommodate mobility aids and adaptable to a variety of accessibility needs.
Design Features
- Modern townhome layouts designed for families of all sizes
- Energy-efficient building systems
- Outdoor landscaping to enhance community connections
- Accessible features to ensure inclusivity
Construction Updates
Work performed to date includes onsite grading and deep utilities, as well as offsite sewer and water connections. Pile foundations have been installed for all blocks. Grade beams for the first blocks have been poured, and this work will continue block-by-block until complete.
Your Questions,
Answered
Contractor hours are Monday–Saturday 7:00 a.m. – 5:30 p.m. (as required on Saturdays).
All tree removals are subject to permitting and approval by the City of Edmonton. New additional trees will be planted throughout the development.
Housing around Edmonton, including existing housing in Ogilvie Ridge, is a similar distance or closer to EPCOR neighbourhood sub-stations.
Join the Ogilvie Ridge
Mailing List
Keep up to date on our Ogilvie Ridge project and receive notifications about upcoming community sessions.